SSC - CDL Building and Industrial Training Building (Phase I)

97%

Status

In Process/Approved [In Process/Approved]

97% complete, updated on Tue 12/17/24 3:28 PM by Shawn Tillotson

Changed Percent Complete from 85% to 97%.

Project Status Report:

SSC - CDL Building and Industrial Training Building (Phase I)

Percent Completed:  85%
Total Budget: $8,800,000.00
Planned Completion Date:  Fri 12/20/24


Summary:

  • Contractor is working on completing the punch list.
  • Certificate of Occupancy from the City of South Sioux City in the near future
  • At the point of Substantial Completion of the CDL Building, as determined by the Architect, that means the facilities are sufficiently complete so the College can occupy or utilize the facility for its intended use,
  • From Network and Infrastructure's end, AV can be completed shortly after Substantial Completion is obtained. ​​​​​​​
  • Per Ed Lewis:
    • Most of our equipment is in storage in SSC that will need to be moved in and assembled.
      • He would like some help with some of the assembly and installation of some of the equipment and storage shelves/cabinets. 
    • TS will work with instructors on how and when the technology (phone and computer) will be transferred for Chris’ office.
    • Ed has contacted the installers of the simulator and the truck lifts. He will let us know how far out their schedules are.

Additional information and links:

N/A
 

Blockers:

None
 

Next Steps:

  1. Confirmation of "Substantial Completion" date
  2. TS will complete AV installations within 5 days of substantial completion date
  3. Physical Plant will work with Tim on assisting with installation of monitors
  4. TS will work with instructors on office completion
  5. Ed will work with Physical Plant to install remaining furniture/shelving
  6. Ed will coordinate installation of simulator and truck lifts​​​​​​​

Details

Dates
Tue 2/1/22 - Fri 12/20/24
Acct/Dept
Workforce Development
Type
Technology Services / Technology Services Project
Health
Green - On track
Portfolio(s)
Classification
GROW: Enhance and expand
Created
Fri 5/3/24 11:18 AM
Modified
Tue 12/17/24 3:28 PM

Northeast Project Management

Relation to Strategic Priorities
Effective Resource Management
Excellence and Innovation in Educational Programs
VP Approval
Does this project have VP Approval.
Yes

Description

An 11,600-square-foot, commercial driver’s license (CDL) truck driving training facility and an adjacent truck driving range, and a 1,500 square-foot addition to Northeast’s existing Industrial Training building to increase capacity of the welding program will be located just to the west of the main extended campus building at 1001 College Way. 

Goals

  1. We are mindful stewards of resources

  2. We aspire to create an inclusive, diverse culture!

  3. We build partnerships and collaborations

  4. We champion student success

  5. We practice continuous improvement

Manager

Alternate Manager(s)

Sponsor

Stakeholders (10)

BR
Bradley Ranslem
Dean of Applied Technology (Applied Technology Department)
Responsible, Accountable, Consulted, Informed
Dean of Applied Technology
Mon 9/23/24 8:39 AM
BM
Brandon McLean
Executive Director of Physical Plant (Physical Plant Department)
Responsible, Accountable, Consulted, Informed
Executive Director of Physical Plant
Mon 9/23/24 8:42 AM
CR
Chance Rohlk
Welding Instructor - SSC (Welding Department)
Responsible, Accountable, Consulted, Informed
Welding Instructor - SSC
Fri 12/13/24 2:31 PM
CA
Christopher Andersen
Truck Driving Trainer - South Sioux City (Truck Driving Department)
Responsible, Accountable, Consulted, Informed
Truck Driving Trainer - South Sioux City
Fri 12/13/24 2:32 PM
EL
Ed Lewis
CDL Program Director (Applied Technology Department)
Responsible, Accountable, Consulted, Informed
CDL Program Director
Fri 12/13/24 2:33 PM
GW
Gage Weller
Custodial / Maintenance Technician - SSC (Custodial Services Department)
Consulted, Informed
Custodial/Maintenance Technician - SSC
Fri 12/13/24 2:30 PM
JH
Jennifer Happold
Executive Assistant, Administrative Services (Administrative Services Department)
Consulted, Informed
Executive Assistant, Administrative Services
Mon 9/23/24 8:41 AM
KT
Katie Towler
Director of Extended Campus, South Sioux City (Extended Campus Department)
Consulted, Informed
Director of Extended Campus, South Sioux City
Mon 9/23/24 8:40 AM
RP
Renee Peters
Executive Director of Security and Technology Services (Security and Technology Services Department)
Consulted, Informed
TS Security Lead
Wed 7/17/24 11:18 AM
SG
Scott Gray
Vice President of Administrative Services and General Counsel (Administrative Services Department)
Responsible, Accountable, Consulted, Informed
Vice President of Administrative Services and General Counsel
Mon 9/23/24 8:41 AM