In Process/Approved [In Process/Approved]
50% complete, updated on Thu 12/19/24 8:53 AM by Shawn Tillotson
Project Status Report: Maclay - New Building Project Percent Completed: 50% Total Budget: $25,800,000.00 Planned Completion Date: Mon 9/1/25 Summary: DWG file sent to Cisco vendor for AP placements. Exterior work being completed as weather permits. Drywall work being completed in vestibules, corridors, hallways and classrooms. Electrical to the building was completed 12/3/2024. Area D and Penthouse data cable trays were being installed. Area D & C, electrical was being pulled in. Additional information and links: N/A Blockers: No delays reported. Next Steps: Upcoming items are installation of tile and carpet Next meeting 1/8/2025
New building construction project. Board of Governor's project.