In Process/Approved [In Process/Approved]
98% complete, updated on Thu 8/21/25 9:45 AM by Shawn Tillotson
Changed Percent Complete from 92% to 98%. Project Status Report: Maclay - New Building Project Percent Completed: 92% Total Budget: $25,800,000.00 Planned Completion Date: Fri 8/15/25 Summary: The meeting on 8/18/2025 focused on final updates and outstanding tasks related to the Maclay building launch and technology setup. Overall, the team reported smooth operations on the first day of classes, with only minor issues noted. Key Updates: Cell Booster Installation: Antennas are being installed; expected completion within a day or two. ABKB Creations Website: Under construction page is live; full site expected by end of the week. ACL Data Tasks: Marked as low priority and placed on hold; may be closed post-project. ECC Punch List: Six minor items remain (e.g., microphone repair, display issue, documentation). Next ECC meeting scheduled for September. Digital Signage: Managed by Student Activities; no further action needed unless content changes are requested. Communication Plan: Informal outreach completed; faculty are aware of support channels and ticketing process. Service Center Activity: Minor issues reported (e.g., Wi-Fi, laser pointer compatibility, whiteboard app); no major concerns. Physical Issues: Marker trays breaking off; handled by Physical Plant via repair@northeast.edu email. Additional information and links: None Blockers: None Next Steps: Action Items Complete Cell Booster Installation Assigned to: Kevin Furstenau Due: Within 1–2 days Status: In progress Finalize ABKB Creations Website Assigned to: Michael Castro Due: End of the week Status: In progress Review ACL Data Tasks Assigned to: Field May & Shawn Tillotson Action: Decide whether to close or convert to post-project tickets Monitor ECC Punch List Completion Assigned to: Field May Due: Before next ECC meeting in September Status: Ongoing Confirm Digital Signage Ownership Assigned to: David Cone Status: Completed (Student Activities owns content) Maintain Visibility and Support Assigned to: All team members Action: Continue presence and responsiveness during initial weeks of classes Track and Respond to Service Center Tickets Assigned to: Darin Watts Status: Ongoing Report Physical Issues Assigned to: All staff Action: Use repair@northeast.edu email for Physical Plant concerns
The meeting on 8/18/2025 focused on final updates and outstanding tasks related to the Maclay building launch and technology setup. Overall, the team reported smooth operations on the first day of classes, with only minor issues noted.
Key Updates:
Cell Booster Installation: Antennas are being installed; expected completion within a day or two.
ABKB Creations Website: Under construction page is live; full site expected by end of the week.
ACL Data Tasks: Marked as low priority and placed on hold; may be closed post-project.
ECC Punch List: Six minor items remain (e.g., microphone repair, display issue, documentation). Next ECC meeting scheduled for September.
Digital Signage: Managed by Student Activities; no further action needed unless content changes are requested.
Communication Plan: Informal outreach completed; faculty are aware of support channels and ticketing process.
Service Center Activity: Minor issues reported (e.g., Wi-Fi, laser pointer compatibility, whiteboard app); no major concerns.
Physical Issues: Marker trays breaking off; handled by Physical Plant via repair@northeast.edu email.
Action Items
New building construction project. Board of Governor's project.