In Process/Approved [In Process/Approved]
60% complete, updated on Tue 7/8/25 10:07 AM by Shawn Tillotson
Project Status Report: Maclay - New Building Project Percent Completed: 60% Total Budget: $25,800,000.00 Planned Completion Date: Fri 8/15/25 Here's a summary and action items from the Maclay Update Meeting held on July 7, 2025: 📝 Meeting Summary 1. Construction & Furniture Installation Project is on schedule. Classroom furniture installation is wrapping up; desking furniture (by Eeks) begins July 14. 2. Technology & Infrastructure Classroom technology: No major updates; equipment ordered long ago. Cell booster: Awaiting coax sourcing; installation expected before school year. Network & UPS: Mostly configured; minor troubleshooting ongoing. Room testing: In progress; KB templates being built. Open houses: Scheduled for start of semester. Applied Connective: Final cable terminations next week. Second UPS: Power installed; waiting for delivery. Security cameras: Physically installed; software setup ongoing. Wireless coverage: Fully installed and confirmed. Paging system: Hardware installation scheduled this week. 3. Occupancy & Moves Updated occupancy list shared via Excel and OneDrive. Active Directory and RE911 updates to begin soon. Faculty move coordination ongoing; only personal items to be moved. 4. Service Center Classroom work progressing well; possibly ahead of schedule. 5. Punch List & Issues Punch list not finalized yet; expected soon. Noise issue in classroom documented as a punch list item. One-year warranty period post-occupancy for issue resolution. ✅ Action Items Owner Task Deadline/Status Shawn Tillotson Share updated occupancy spreadsheet link in meeting chat ✅ Completed Field May Begin Active Directory updates and RE911 configuration This/next week Kevin Furstenau Finalize camera setup in Milestone software In progress Applied Connective Terminate remaining cables Next week Ethan Complete paging hardware installation This week Kevin, Mike, Field Conduct open houses at McClay Around semester start Construction Team Finalize punch list and address noise issue Ongoing All Monitor PR 737 floor box for condensation Ongoing
Here's a summary and action items from the Maclay Update Meeting held on July 7, 2025:
1. Construction & Furniture Installation
3. Occupancy & Moves
4. Service Center
5. Punch List & Issues
New building construction project. Board of Governor's project.