Maclay - New Building Project

58%

Status

In Process/Approved [In Process/Approved]

58% complete, updated on Wed 5/14/25 1:22 PM by Shawn Tillotson

Project Status Report:

Maclay - New Building Project

Percent Completed:  58%
Total Budget: $25,800,000.00
Planned Completion Date:  Mon 7/21/25


Summary:


Project Update Report from Technology Services: Maclay Building
Date: May 12, 2025
 

General Updates
  • Project Schedule: Still on track. Next Hausman/OAC meeting scheduled for June 4 at 9:30 AM.
  • Furniture Installation: First meeting scheduled for May 14. Led by Chris Rutten. Direct furniture questions to Chris or Shawn.
  • Classroom Ed Services Scheduling Plans:
    • Plan A: Use current class locations.
    • Plan B: Transition to Maclay if ready.
    • Need to ensure technology in Maclay supports scheduled classes (hardware/software compatibility).

Technology & Infrastructure
  • Learning Technology Standards: Finalization needed. Information to be shared with CT&L. 
  • Software Requirements:
    • Create a comprehensive list of software required per course to align with classroom setup.
  • Network & AV Progress (per Field May):
    • All network switches racked, pending connection post-change freeze.
    • Wireless Access Point installation to begin this week.
    • AV installation by ECC is underway (Crestron, screens), based on existing documentation.
    • Remote access (Zoho Assist) set up for ECC.
    • Some network drops pending furniture arrival (8 drops).
  • Computer Equipment:
    • All computers received.
    • Four additional printers secured: lease terms pending.

Construction & Site Notes
  • Model Electric uncovered existing conduit while drilling; no damage reported. Investigating whether conduit is active or abandoned.

 

Additional information and links:

None reported.
 

Blockers:

None reported. 
 

Next Steps:

Action Items
Task Owner Due
Confirm classroom tech installation list Shawn Tillotson May 31
Install wireless access points Field May Week of May 12
Connect network after change freeze ends Field May, Jake Week of May 12
Complete furniture-related drops Applied Connect (post furniture delivery) TBD
Verify conduit status with Kevin Field May May 13
Monitor leasing process for printers Darin Watts Ongoing

Details

Dates
Fri 10/1/21 - Mon 7/21/25
Acct/Dept
Administrative Services
Type
Technology Services / Technology Services Project
Health
Green - On track
Portfolio(s)
Classification
GROW: Enhance and expand
Created
Tue 4/30/24 4:54 PM
Modified
Wed 5/14/25 1:22 PM

Northeast Project Management

Relation to Strategic Priorities
Effective Resource Management
VP Approval
Does this project have VP Approval.
Yes

Description

New building construction project. Board of Governor's project.

Goals

  1. We practice continuous improvement

Manager

Alternate Manager(s)

Sponsor

Stakeholders (1)

SG
Scott Gray
Vice President of Administrative Services and General Counsel (Administrative Services Department)
Responsible, Accountable, Consulted, Informed
Vice President of Administrative Services and General Counsel
Wed 3/5/25 11:32 AM