Maclay - New Building Project

50%

Status

In Process/Approved [In Process/Approved]

50% complete, updated on Thu 12/19/24 8:53 AM by Shawn Tillotson

Project Status Report:

Maclay - New Building Project

Percent Completed:  50%
Total Budget: $25,800,000.00
Planned Completion Date:  Mon 9/1/25

Summary:

  • DWG file sent to Cisco vendor for AP placements.
  • Exterior work being completed as weather permits. 
  • Drywall work being completed in vestibules, corridors, hallways and classrooms.
  • Electrical to the building was completed 12/3/2024.
    • Area D and Penthouse data cable trays were being installed.
    • Area D & C, electrical was being pulled in. 

Additional information and links:

N/A 
 

Blockers:

No delays reported. 
 

Next Steps:

  • Upcoming items are installation of tile and carpet
  • Next meeting 1/8/2025

Details

Dates
Fri 10/1/21 - Mon 9/1/25
Acct/Dept
Administrative Services
Type
Technology Services / Technology Services Project
Health
Green - On track
Portfolio(s)
Classification
GROW: Enhance and expand
Created
Tue 4/30/24 4:54 PM
Modified
Thu 12/19/24 8:53 AM

Northeast Project Management

Relation to Strategic Priorities
Effective Resource Management
VP Approval
Does this project have VP Approval.
Yes

Description

New building construction project. Board of Governor's project.

Goals

  1. We practice continuous improvement

Manager

Alternate Manager(s)

Sponsor